    Applus+ has been working on an offshore gas project located on the English and Dutch continental shelf since January 2020. Two production wells have now been completed and the Oil & Gas company is currently drilling a third exploration well. If everything goes according to plan, the third well will supply gas in the fourth quarter of this year.

    Applus+ has assessed whether the 2 hook-up spools were commissioned in accordance with the applicable guidelines: PED 2014/68 / EU Module G (new construction phase) and also in accordance with the Pressure Equipment Commodities Act Decree 2016, article 21 (user phase). A hook-up is the connection of the well to the Christmas tree, which consists of source equipment used to safely remove gas from the well.

    Despite the COVID-19 outbreak, the production wells were commissioned without incidents, within budget and according to schedule. We carried out the conformity assessments and offshore inspection before commissioning. 

    The PED 2014/68 / EU Module G Conformity Assessments contemplates these steps:

    • Examination of the technical documentation related to the design and manufacturing procedures;
    • Assessment of the materials used if they do not comply with the relevant harmonised standards or didn’t obtain European approval for pressure equipment materials, and check-up of the certificate issued by the manufacturer of the material;
    • Approval of the procedures for the permanent connection of parts, or verification that they have been previously approved;
    • Verification of the qualifications or approvals required;
    • Execution of the final inspection.

    If there are no irregularities, Applus+, as EU-CBIT certified company, provides a Certificate of Conformity (CoC) as Applus+ Norcontrol. 

    An Inspection for Commissioning in accordance with the Pressure Equipment Commodities Act Decree 2016, article 21, consists of the following inspection activities:

    • Verification of the pressure equipment according to the instructions for use and markings. Check-up of the external condition of the pressure equipment;
    • If applicable, check-up of the operation of safety and pressurized fittings;
    • Check-up of the arrangement of the pressure equipment;
    • Report on findings,  final assessment and retest period on the worksheet;
    • Issuing of the Declaration of Commissioning VvI and, if necessary, setting conditions for the use of the pressure equipment and/or the validity of the statement.

    If there are no irregularities, Applus+, as NL-CBIT certified company, issue a VvI.

    Since the project has been a success and the gas field produces in a satisfactory manner, the 3rd well and the 3rd hook-up spool will begin soon. The effort, professionalism and execution of the work has been noticed by the Oil & Gas Company and Applus+ has received compliments for this.

    Our Senior Inspector Paul Kersbergen explains: "It is great to be involved as a supervisor in such a special project. I look forward to carrying out the same inspections in autumn before using the third production well."

    Applus+ uses first-party and third-party cookies for analytical purposes and to show you personalized advertising based on a profile drawn up based on your browsing habits (eg. visited websites). You can accept all cookies by pressing the "Accept" button or configure or reject their use. Consult our Cookies Policy for more information.